The proposed 45.4m road is a dual 4-lane, approximately 800m long which will have an intersection with existing Tampines Road with proper traffic arrangements. The road will cross the existing Sungei Serangoon Canal, which is to be provided with a 3-cell box culvert crossing with maintenance access.
The project also includes Trunk Sewers of 1800mm diameter with depth varying from 12m to 16m, minor sewers of 400mm diameter with depth of 10.5m, roadside drains and box culverts for spans varying from 1.1m to 2.5m and depths up to 2.7m, and a 3-cell box culvert crossing which have been design based on LTA loadings requirements.